KRISHNA HERITAGE

MahaRERA P51700007118Caution

by SHREE BALAJI CONSTRUCTION

S NO 30 H NO 7A PART, KALYAN, 421301

Official record
Dec 2020
Possession
75%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 75%.

Promoter

Builder profile

Builder
SHREE BALAJI CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700007118
Status
New
Stage
Certificate Signed
Possession
December 2020
Construction
75% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Planting80%
Street Lighting50%
Community Buildings50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space75%

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of KRISHNA HERITAGE — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching KRISHNA HERITAGE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.