Under construction

SHETH ZURI

by Sheth Developers Private Limited

OUT OF SURVEY NO 85/1P, 81/1A, 83/2, 83/5, 85/2, 85/3, 85/4P, 85/5, Thane, 400601

High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • 68 RERA complaints. 68 complaint records are disclosed against this project on MahaRERA.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700007274
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
88.9% complete
Units sold
704 of 717

RERA complaint record68 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply65%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting62%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
35
Unit mix
709 res ยท 8 comm
Architect
Bipin Nannaware

Buyer community

Connect with other buyers and owners of SHETH ZURI โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHETH ZURI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.