All RERA projects
๐๏ธ
Mar 2028
Possession
81.3%
Built
30
Complaints
142
Units
High risk
- Possession delayed ~9 yrs. Originally promised Nov 2018, now proposed Mar 2028 per the RERA filing.
- 30 RERA complaints. 30 complaint records are disclosed against this project on MahaRERA.
Official RERA facts
- Registration
- P51700008568
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2028originally November 2018
- Construction
- 81.3% complete
- Units sold
- 140 of 142
RERA complaint record30 records
Complaint data not yet synced for this project.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Planting90%
Street Lighting95%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 11
- Unit mix
- 130 res ยท 12 comm
- Architect
- PRAMOD PATIL AND ASSOCIATES
Buyer community
Connect with other buyers and owners of THE CHALETS AVENUE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching THE CHALETS AVENUE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.