PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHILPA CHS

by YASH INFRA

C.T.S 112/5/5 T.No-12, Thane, 400602

High risk
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Andheri East / MarolMid-income

Office corridors (SEEPZ, MIDC) with value housing pockets between them.

Growth drivers:
Airport proximity, Metro 1/7, IT-park employment.
Who buys here:
Working couples prioritising commute over frills.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700009903
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)5%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting3%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station5%

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of SHILPA CHS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHILPA CHS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.