PropPin
All RERA projects
🏗️
Under construction

MAHAVEER HEAVENS PHASE I

by MAHAVEER INFRASTRUCTURE PVT LTD

PLOT NO. 3, SURVEY NO. 30/1/8, 29/11, 35/1/1, 30/1/12/1, GANDHAR NAGAR, 421301

Dec 2023
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700013285
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Sept 2017
Floors
9

Buyer community

Connect with other buyers and owners of MAHAVEER HEAVENS PHASE I — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching MAHAVEER HEAVENS PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.