All RERA projects
๐๏ธ
Dec 2026
Possession
71.1%
Built
0
Complaints
447
Units
Caution
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700013810
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 71.1% complete
- Units sold
- 228 of 447
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths90%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains95%
Landscaping & Tree Planting80%
Street Lighting90%
Community Buildings75%
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal80%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Space80%
Open Parking80%
Building & registration
- RERA registered
- Oct 2017
- Floors
- 8
- Unit mix
- 417 res ยท 30 comm
- Architect
- SACHIN DILIP GULVE
Buyer community
Connect with other buyers and owners of SHREE GAJANAN FORTUNE CITY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHREE GAJANAN FORTUNE CITY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.