Capsule Business Hub

by Maa Vaishnavi Builders & Developers

2848A/1/1, KALYAN, 421301

Dec 2026
Possession
49.1%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 49.1%.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700015836
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
49.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Mar 2018
Floors
9

Buyer community

Connect with other buyers and owners of Capsule Business Hub — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Capsule Business Hub. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.