3,4,4A, Thane, 400614

Dec 2027
Possession
9.1%
Built
0
Complaints
42
Units
High risk
  • Possession delayed ~5 yrs. Originally promised May 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Navi Mumbai (Vashi–Nerul)Mid-income

Planned-city order — wide roads, node markets, established social infra.

Growth drivers:
Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
Who buys here:
Professionals wanting planned-city living with airport-corridor upside.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700017140
Status
New
Stage
Certificate Signed
Possession
December 2027originally May 2023
Construction
9.1% complete
Units sold
11 of 42

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2018
Floors
11
Unit mix
39 res · 3 comm

Buyer community

Connect with other buyers and owners of BHUMIRAJ HILLS — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching BHUMIRAJ HILLS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.