Under construction
Vishnu Vatika Wing C Phase II
Survey No.131, Hissa No. 2 and 4, Badlapur Gaon, 421503
Dec 2026
Possession
89.8%
Built
0
Complaints
109
Units
High risk
- Possession delayed ~4 yrs. Originally promised May 2023, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700020130
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally May 2023
- Construction
- 89.8% complete
- Units sold
- 78 of 109
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting92%
Street Lighting90%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements88.32%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2019
- Floors
- 14
- Unit mix
- 103 res ยท 6 comm
- Architect
- M Square Architects
Buyer community
Connect with other buyers and owners of Vishnu Vatika Wing C Phase II โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Vishnu Vatika Wing C Phase II. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.