Under construction

DIAMOND PALACE

by GULAMSHAH AZGAR ALI

SNO 24 HISSA NO 10 11 8 PT, NAVI BASTI, 421302

Dec 2026
Possession
86.4%
Built
0
Complaints
147
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700021328
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
86.4% complete
Units sold
46 of 147

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station10%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2019
Floors
8
Unit mix
147 res ยท 0 comm
Architect
IRFAN MIYAJI

Buyer community

Connect with other buyers and owners of DIAMOND PALACE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DIAMOND PALACE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.