PropPin
All RERA projects
🏗️
Under construction

SHREE DATTA ASHIRWAD

MahaRERA P51700022431High risk

by SHREE DATTA DEVELOPERS

SURVEY NO. 7A/7/32, PLOT NO. 32, AT- BELAVALI, 421503

Official record
Dec 2022
Possession
9.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 9.1%.

Promoter

Builder profile

Builder
SHREE DATTA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700022431
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
9.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2019
Floors
6

Buyer community

Connect with other buyers and owners of SHREE DATTA ASHIRWAD — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SHREE DATTA ASHIRWAD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.