Under construction

MARATHE TOWER

by SAIJI DEVELOPERS

111, MANDA VILLAGE, 421605

Jul 2026
Possession
83.2%
Built
0
Complaints
218
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700022652
Status
New
Stage
Certificate Signed
Possession
July 2026originally March 2026
Construction
83.2% complete
Units sold
75 of 218

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2019
Floors
66
Unit mix
191 res ยท 27 comm
Architect
Vijay Pandey And Associates

Buyer community

Connect with other buyers and owners of MARATHE TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MARATHE TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.