Under construction
TEN X HABITAT Raymond Realty Tower K
126B/2 Part, 126B-1/1 Part, Thane, 400606
High risk
- 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 90.9%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Sept 2025 per the RERA filing.
Official RERA facts
- Registration
- P51700022940
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2025
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record9 records
- ComplaintCC125030802 Sept 2025Raymond Limited vs Shweta Shinde
- ComplaintCC00600000021016625 Feb 2022Raymond Limited vs Shamrao Ramchandra Nichat and Sonal Umesh NichatSD disposal order CC-210166.pdf on MahaRERA
- ComplaintCC00600000021016725 Feb 2022Raymond Limited vs Ramesh Vithal Lakhmani09,10_Order_2101067 signed.pdf on MahaRERA
- ComplaintCC00600000021016825 Feb 2022Raymond Limited vs Shilpa Lakhmani and Yogesh Lakhmani09,10_Order_2101067 signed.pdf on MahaRERA
- ComplaintCC0060000002099599 Feb 2022Raymond Limited vs Mrs Lalita Ramesh Paila & Mr. Ramesh Chandrashekhram Paila52 TO 56 signed.pdf on MahaRERA
- ComplaintCC0060000001975137 Jul 2021SACHIN HARI DEOKAR vs RAYMOND REALTYSr 19 & 20 CC006000000197538 & anr_ DEEPAK HARI DEOKAR & anr VS RAYMOND REALTY signed.pdf on MahaRERA
- ComplaintCC0060000001975387 Jul 2021DEEPAK HARI DEOKAR vs RAYMOND REALTYSr 19 & 20 CC006000000197538 & anr_ DEEPAK HARI DEOKAR & anr VS RAYMOND REALTY signed.pdf on MahaRERA
- ComplaintCC00600000019734220 Jun 2021Ms. Metali Ketan Gupte vs Raymond LimitedOrder CC006-197342 dated 20-10-2021V.pdf on MahaRERA
- ComplaintCC00600000019565315 Jan 2021SAMIR HARIDAS THAKKAR and SANGEETA SAMIR THAKKAR vs Raymond Realty52 TO 56 signed.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Nov 2019
- Floors
- 44
Buyer community
Connect with other buyers and owners of TEN X HABITAT Raymond Realty Tower K โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching TEN X HABITAT Raymond Realty Tower K. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.