Under construction

SILVIA

by IMPRESSIONS NXT

SURVEY NO 229 OLD, 04 NEW, HISSA NO 05 PART, NAVAPADA, 421202

Mar 2027
Possession
49.1%
Built
0
Complaints
1
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 49.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700023372
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2023
Construction
49.1% complete
Units sold
0 of 1

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2019
Floors
5
Unit mix
1 res ยท 0 comm

Buyer community

Connect with other buyers and owners of SILVIA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SILVIA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.