Under construction

Padamavati Royal Phase 2

by Sujeet Kumar Jeetpratap Singh

81/1, 98/3A, 101/2, 102, 103/1, TITWALA, 421605

Dec 2029
Possession
61.5%
Built
0
Complaints
600
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Nov 2025, now proposed Dec 2029 per the RERA filing.

Official RERA facts

Registration
P51700023536
Status
New
Stage
Certificate Signed
Possession
December 2029originally November 2025
Construction
61.5% complete
Units sold
430 of 600

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Dec 2019
Floors
17
Unit mix
600 res ยท 0 comm
Architect
Cogent Consultant

Buyer community

Connect with other buyers and owners of Padamavati Royal Phase 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Padamavati Royal Phase 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.