SPM Lake City Phase II Part 1

by KOTHARI & DESHMUKH LANDMARK LLP

Survey No 56 Hissa No 2, Karav Village, 421503

Nov 2028
Possession
61.2%
Built
1
Complaints
199
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Jan 2026, now proposed Nov 2028 per the RERA filing.

Official RERA facts

Registration
P51700024808
Status
New
Stage
Certificate Signed
Possession
November 2028originally January 2026
Construction
61.2% complete
Units sold
68 of 199

RERA complaint record1 record

  • ComplaintCC126026628 May 2026
    INDRAJEET PRALHAD SURYAWANSHI vs KOTHARI & DESHMUKH LANDMARK LLP

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2020
Floors
6
Unit mix
199 res ยท 0 comm

Buyer community

Connect with other buyers and owners of SPM Lake City Phase II Part 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SPM Lake City Phase II Part 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.