Under construction

Regency Antilia Phase V Avana

by REGENCY NIRMAN LTD

S. No. 40, 41, 42, 43, 44, 46, 47, 48, 49, 50, 51 , 52, 54, 55, 56, 57, 58, CTS No.279/1 to 6, Ulhasnagar, 421001

Oct 2024
Possession
90.9%
Built
2
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2024) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2024 per the RERA filing.

Official RERA facts

Registration
P51700026760
Status
New
Stage
Certificate Signed
Possession
October 2024
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Storm Water Drains90%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal70%
Water conservation /Rain water harvesting70%
Energy managemcnt20%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2020
Floors
29

Buyer community

Connect with other buyers and owners of Regency Antilia Phase V Avana โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Regency Antilia Phase V Avana. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.