Under construction

Sai Galaxy B-WingMahaRERA P51700027863

by Jash Developers

S.NO.10/2, PADALE, 421204

Jun 2026
Possession
90.9%
Built
0
Complaints
29
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Official RERA facts

Registration
P51700027863
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
90.9% complete
Units sold
27 of 29

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2021
Floors
8
Unit mix
21 res ยท 7 comm
Architect
Jitesh P. Pawar & Associates

Buyer community

Connect with other buyers and owners of Sai Galaxy B-Wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sai Galaxy B-Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.