Under construction

FENKIN EMPIRE

by FEN-KIN REALTORS & PROJECT PVT LTD

CTS NO 313 AND 314B, THANE WEST, 400601

Jul 2023
Possession
88.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jul 2023) has passed with construction at 88.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2023 per the RERA filing.

Official RERA facts

Registration
P51700030249
Status
New
Stage
Certificate Signed
Possession
July 2023
Construction
88.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting70%
Energy managemcnt90%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Open Parkingnot started

Building & registration

RERA registered
Aug 2021

Buyer community

Connect with other buyers and owners of FENKIN EMPIRE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FENKIN EMPIRE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.