Runwal Gardens Phase 4 Bldg No. 35-36
by Runwal Residency Private Limited
SURVEY NOS. 44/5APT, 44/5B PT, 44/8PT, 44/9PT, 44/12PT, 50/2PT, 50/3PT OF VILLAGE GHARIVALI, Dombivali, 421201
- Possession delayed ~1 yr. Originally promised Mar 2026, now proposed Mar 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700031319
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally March 2026
- Construction
- 66.4% complete
- Units sold
- 421 of 564
RERA complaint record3 records
- ComplaintCC1250373023 Oct 2025PRANIT VASANT LAKDE vs Runwal Residency Private Limited
- ComplaintCC1250096820 Mar 2025KIRAN KRISHNA SURVE vs Runwal Residency Private Limited
- ComplaintCC0060000002102031 Mar 2022Lokesh Kumar vs Runwal Residency Pvt. Ltd.Order of Lokesh Kumar.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2021
- Floors
- 35
- Unit mix
- 564 res ยท 0 comm
- Architect
- Saakar Architects
Buyer community
Connect with other buyers and owners of Runwal Gardens Phase 4 Bldg No. 35-36 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Runwal Gardens Phase 4 Bldg No. 35-36. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.