PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

BALAJI ESTATE PHASE 2

by M/S SAI BALAJI BUILDCON

SURVEY NO 18/5, 18/6, 20, 41-1/4, KHONI UMBROLI ROAD, 421204

Dec 2026
Possession
24.5%
Built
0
Complaints
789
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 24.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700031992
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
24.5% complete
Units sold
491 of 789

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2021
Floors
26
Unit mix
789 res ยท 0 comm
Architect
STHAPATYA NIRMAAN

Buyer community

Connect with other buyers and owners of BALAJI ESTATE PHASE 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BALAJI ESTATE PHASE 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.