PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHIVANJALI HEIGHTS

by SHIVANJALI CONSTRUCTION

SURVEY NO 73, 74, 75, 76,77, 78, 79, BADLAPUR WEST, 421503

Jun 2023
Possession
50%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 50%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.
Thane (Ghodbunder belt)Mid-income

A full city of its own โ€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700032585
Status
New
Stage
Certificate Signed
Possession
June 2023originally June 2022
Construction
50% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2022
Floors
10

Buyer community

Connect with other buyers and owners of SHIVANJALI HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIVANJALI HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.