PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

THANEKAR PALACIO

by THANEKAR REALTOR LLP

SURVEY NO 82 H NO 2/1 PART, BADLAPUR, 421503

Dec 2024
Possession
61.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 61.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.

Official RERA facts

Registration
P51700032795
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
61.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2022
Floors
18

Buyer community

Connect with other buyers and owners of THANEKAR PALACIO โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THANEKAR PALACIO. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.