Under construction

Runwal Gardens Phase 4 Bldg No. 37

by Runwal Residency Private Limited

44/5 part 23/1 part Gharivali, Dombivali, 421204

Jun 2027
Possession
55.6%
Built
7
Complaints
282
Units
High risk
  • Possession delayed ~1 yr. Originally promised Mar 2026, now proposed Jun 2027 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51700033206
Status
New
Stage
Certificate Signed
Possession
June 2027originally March 2026
Construction
55.6% complete
Units sold
239 of 282

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2022
Floors
35
Unit mix
282 res ยท 0 comm
Architect
Saakar Architects

Buyer community

Connect with other buyers and owners of Runwal Gardens Phase 4 Bldg No. 37 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Runwal Gardens Phase 4 Bldg No. 37. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.