LAKE EMERALD- PHASE I

by N D ENTERPRISES

PLOT NO 2 TO 92 AS PER TP PLAN GUT NO 1181 1182 1183, NAGAON, 421401

Apr 2027
Possession
โ€”
Built
0
Complaints
91
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Apr 2025, now proposed Apr 2027 per the RERA filing.

Official RERA facts

Registration
P51700033779
Status
New
Stage
Certificate Signed
Possession
April 2027originally April 2025
Construction
โ€”
Units sold
20 of 91

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths37%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Planting15%
Street Lightingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space11%
Open Parkingnot started

Building & registration

RERA registered
Mar 2022
Architect
MANDAR JAYANT LELE

Buyer community

Connect with other buyers and owners of LAKE EMERALD- PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LAKE EMERALD- PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.