PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Liana B

by LODHA DEVELOPERS LIMITED

65/15A (pt), Kalyan, 421203

High risk
  • Possession date passed. The proposed possession date (Feb 2026) has passed with construction at 73%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Feb 2026 per the RERA filing.

Official RERA facts

Registration
P51700033964
Status
New
Stage
Certificate Signed
Possession
February 2026
Construction
73% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains40%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2022
Floors
24

Buyer community

Connect with other buyers and owners of Liana B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.