Under construction

ASHAR ARIZE N.M.M. SOCIETY TOWER A

by Ms ASHAR VENTURES

2459, 2460, 2461, 2490, 2491, 2492, 2546, 2547, Thane, 400605

High risk
  • Behind schedule. Possession is due Jan 2027 but construction is only at 7.3%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jan 2027 per the RERA filing.

Official RERA facts

Registration
P51700034565
Status
New
Stage
Certificate Signed
Possession
January 2027
Construction
7.3% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
SOCIETY OFFICEnot started
COMMUNITY HALLnot started
BOX CRICKETnot started

Building & registration

RERA registered
Apr 2022
Floors
35

Buyer community

Connect with other buyers and owners of ASHAR ARIZE N.M.M. SOCIETY TOWER A โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ASHAR ARIZE N.M.M. SOCIETY TOWER A. Real notes from real buyers beat any brochure.