Under construction

SAIRAJ HEIGHTS

by VPM JAIRAJ DEVELOPERS

4/2/4/4/4/5/4/6, TEMGHAR VILLAGE, 421308

Mar 2027
Possession
35.2%
Built
0
Complaints
201
Units
Caution
  • Behind schedule. Possession is due Mar 2027 but construction is only at 35.2%.

Official RERA facts

Registration
P51700034679
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
35.2% complete
Units sold
72 of 201

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2022
Floors
25
Unit mix
196 res ยท 5 comm
Architect
H K DESIGN CONSULTANTS

Buyer community

Connect with other buyers and owners of SAIRAJ HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAIRAJ HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion