Under construction

SILVER SQUARE

by RAMDEV VENKATESH HOUSING

SNO 558 OLD 208 SNO NEW HNO 1, SNO 568 OLD 218 NEW HNO 4,5, SNO 555 OLD 216 NEW HNO 7, SNO 562 OLD 206 NEW HNO 2,4, BHAYADNER, 401107

Dec 2026
Possession
32.7%
Built
0
Complaints
48
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 32.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700045618
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
32.7% complete
Units sold
27 of 48

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
May 2022
Floors
11
Unit mix
28 res ยท 20 comm
Architect
ANISH AND ASSOCIATES

Buyer community

Connect with other buyers and owners of SILVER SQUARE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SILVER SQUARE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.