Under construction

ASHTAVINAYAK

by PARISPARSH

980,981,984,983, SAI BABA MANDIR, 421201

Apr 2025
Possession
10%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2025) has passed with construction at 10%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2025 per the RERA filing.

Official RERA facts

Registration
P51700046185
Status
New
Stage
Certificate Signed
Possession
April 2025
Construction
10% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Jun 2022
Floors
9

Buyer community

Connect with other buyers and owners of ASHTAVINAYAK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ASHTAVINAYAK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.