Under construction

GANPATI PRASANNA

by VIJAY PRABHAKAR PATIL

SURVEY NO 214 HISSA NO 7B AND 7C, TITWALA EAST, 421605

Dec 2026
Possession
45.9%
Built
0
Complaints
45
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 45.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700048517
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
45.9% complete
Units sold
34 of 45

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Jan 2023
Floors
7
Unit mix
42 res ยท 3 comm
Architect
DE CON CONSULTANTS

Buyer community

Connect with other buyers and owners of GANPATI PRASANNA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GANPATI PRASANNA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.