Under construction

DEV ELLANZA

by DLS ENTERPRISES

SURVEY NO 16 H NO 4/2, TITWALA, 421605

Apr 2027
Possession
51.4%
Built
0
Complaints
117
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P51700048647
Status
New
Stage
Certificate Signed
Possession
April 2027originally April 2026
Construction
51.4% complete
Units sold
32 of 117

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements15%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2023
Floors
15
Unit mix
105 res ยท 12 comm
Architect
VIJAY PANDEY & ASSOCIATES

Buyer community

Connect with other buyers and owners of DEV ELLANZA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DEV ELLANZA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.