PITRUCHHAYAMahaRERA P51700049256

by Sandeep Ramchandra Bhave

53/B/15 Tikka no 15, Vishnu Nagar Naupada, 400602

Dec 2026
Possession
27.3%
Built
0
Complaints
24
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 27.3%.

Official RERA facts

Registration
P51700049256
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
27.3% complete
Units sold
2 of 24

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2023
Floors
7
Unit mix
24 res ยท 0 comm
Architect
Ten folds

Buyer community

Connect with other buyers and owners of PITRUCHHAYA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PITRUCHHAYA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.