- Possession delayed ~2 yrs. Originally promised Jul 2024, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Central-line volume market — affordable towers around busy junctions.
- Growth drivers:
- Metro 5, ring-road plans, the region's most accessible pricing.
- Who buys here:
- Budget-first buyers who commute the central line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700051267
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally July 2024
- Construction
- 75% complete
- Units sold
- 37 of 59
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EXT51700024407Revised to June 2025
1) Initially we have taken three plots for development later stage one more adjacent plot’s development was merged with this ongoing development. After execution of the redevelopment agreement sanction of the revised plans and permission to construct took the time to start the construction work. 2) After all the permissions are in place there was shortage of Labors in the said area as various redevelopment are going on and most of the labor’s migration to native place in summer.
- EA23092502665Revised to December 2026
1) Due to an unforeseen personal emergency, the appointed contractor had to return to his native place, resulting in the unavailability of both the contractor and his labour team. During this interim period, we initiated the process of identifying and onboarding a suitable replacement contractor. Given the due diligence required for selection, negotiations, and mobilization of a new workforce, there was an unavoidable delay in resuming site activities 2) The finishing work experienced a slight delay due to the unavailability of quality-approved materials. As we are committed to maintaining high construction standards and do not compromise on the quality of workmanship or materials used, we opted to wait for the appropriate materials to be procured. This approach ensures the integrity and long-term durability of the project.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jun 2023
- Floors
- 7
- Unit mix
- 49 res · 10 comm
- Architect
- SATISH KANADE
- Plot / CTS / survey no.
- SURVEY NO 42A, HISSA NO 19/A/3 CTS No. 7273 TO 7276, SURVEY No. 42/A, HISSA No. 19/A/8 CTS No.7277 TO 7280, SURVEY No 42/A, HISSA No 19/A/6, SURVEY NO 130 HISSA No. 3A/1 CTS No 7281 TO 7283
- Planning authority
- KDMC
- Approved layout land
- 940 sq.m
- Land for this registration
- 940 sq.m
- Recreational open space
- 940 sq.m
- Permissible built-up area
- 3,110.42 sq.m
- Registered office
- NEAR MARUTI MANDIR
- North
- 73 08 40 8
- South
- 0
- East
- 19 14 39 9
- West
- 0
Buyer community
Connect with other buyers and owners of VAISHNAVI HEIGHTS — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching VAISHNAVI HEIGHTS. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.