PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Kerala Village Phase-2

by JOHN MATHEW

Survey No.396(Pt ), 397 ( Pt ) & 399, Near Shenwa Naka, 421601

Mar 2027
Possession
70.5%
Built
0
Complaints
127
Units
Caution
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700051512
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2025
Construction
70.5% complete
Units sold
71 of 127

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains90%
Landscaping & Tree Planting90%
Street Lighting35%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Space65%
Open Parking75%

Building & registration

RERA registered
Jun 2023
Floors
8
Unit mix
127 res ยท 0 comm
Architect
John Varghese

Buyer community

Connect with other buyers and owners of Kerala Village Phase-2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kerala Village Phase-2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.