SIDDHIVINAYAK RESIDENCYMahaRERA P51700051622

by REEVA REALITY DEVELOPERS

SURVEY NO 104 HISSA NO 14, TITWALA, 421605

Dec 2029
Possession
52.3%
Built
0
Complaints
92
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Jun 2027, now proposed Dec 2029 per the RERA filing.

Official RERA facts

Registration
P51700051622
Status
New
Stage
Certificate Signed
Possession
December 2029originally June 2027
Construction
52.3% complete
Units sold
9 of 92

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2023
Floors
8
Unit mix
86 res ยท 6 comm
Architect
DE CON CONSULTANTS

Buyer community

Connect with other buyers and owners of SIDDHIVINAYAK RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SIDDHIVINAYAK RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.