PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Nivasa Green City Phase 1

MahaRERA P51700080070Clean record

by Nivasa Developers

Survey No 91 Hissa No 2, 3, 4, 5 and 7C, Survey No 47 Hissa No 1 Survey No 79 Hissa No 2 and 3/A/1, Dombivli, 421201

Official record
Dec 2030
Possession
13.6%
Built
0
Complaints
376
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700080070
Status
New
Stage
Certificate Signed
Possession
December 2030
Construction
13.6% complete
Units sold
51 of 376

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Smt.Baya Ratan Mhatre, Shri Nitin Ratan Mhatre, Usha Harishchandra Mhatre, Shri Devendra Harishchandra Mhatre, Shri Rajendra Harishchandra Mhatre, Shri Yogendra Harishchandra Mhatre, Shri Jitendra Harishchandra Mhatre, Mohan Sawalaram Mhatre, Pournima Ajay More, Fulaji Sawalaram Mhatre, Bholenath Waman Mhatre, Ashtavinayak Enterprises, Nivas Gajanan Mhatre, Shri Arun Bhagwan Mhatre, Gurunath Gajanan Mhatre, Smt. Shantabai Gajanan Mhatre, Rajubai Barkya Mhatre, Shri Vishnu Ganpat Mhatre, Shri Eknath Ganpat Mhatre, Ramakant Waman Mhatre, Vithal Sawalaram Mhatre, Saraswati Motiram Mhatre, Suman Waman Mhatre, Baliram Atmaram Patil, Bharat Atmaram Patil, Gurunath Atmaram Patil, Sharad Atmaram Patil, Krishnabai Gangaram Thakur, Sunanda Bhaskar Naik, Shri Namdev Hashya Mhatre, Smt. Jijabai Shivram Mali, Gangubai Krishna Mhatre, Pratibha Chandrakant Bhoir, Manisha Rajesh Mhatre

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths30%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Apr 2025
Floors
22
Unit mix
376 res ยท 0 comm
Architect
Space Enviro
Plot / CTS / survey no.
Survey No 91 Hissa No 2, 3, 4, 5 and 7C, Survey No 47 Hissa No 1 Survey No 79 Hissa No 2 and 3/A/1
Planning authority
KALYAN DOMBIVALI MUNICIPAL CORPORATION
Approved layout land
16,250 sq.m
Land for this registration
16,250 sq.m
Recreational open space
1,608 sq.m
Permissible built-up area
62,204.97 sq.m
Registered office
Om Residency
Plot boundaries
North
River Front
South
Survey No 80
East
River Front
West
DFC Line
Parking
268 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • UNION BANK OF INDIA โ€” 149419
    IFSC UBIN0572047
    ARTI NAGARI-KALYAN WEST SHOP NO 3-8, SABARMATI CHS LTD, WAYLE NAGAR KALYAN MAHARASHTRA PINCODE-421301

Commencement Certificate documents

  • S041000303_2402141832000.pdf
  • Revised CC.pdf

Buyer community

Connect with other buyers and owners of Nivasa Green City Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Nivasa Green City Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.