Haware Paramount Kalyan Phase IV
Survey No - 3/2 (Pt), 4/16 (Pt), Muthaval, Bhiwandi, 421302
- Mortgaged to a lender (โน35 Cr). MahaRERA's financial encumbrance declaration shows this project has โน35 Cr secured against a lender โ a lender's claim can outrank a buyer's if the promoter defaults.
Official RERA facts
- Registration
- P51700080192
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028
- Construction
- 10% complete
- Units sold
- 49 of 79
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
MahaRERA's financial encumbrance declaration shows this project has โน35 Cr secured against a lender. If the promoter defaults, the lender's claim can outrank a buyer's โ worth raising with the builder before booking.
Landowner
Sakhubai Namdev Bhamre, Fashibai Namdev Bhamre, Chhatrapati Arjun Bhamre, Jitendra Arjun Bhamre, Subhash Pandurang Bhamre, Sandeep Pandurang Bhamre, Jagdish Namdeo Bhamre, Bhushan Namdev Bhamre, Namdev Kathod Patil
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2025
- Floors
- 8
- Unit mix
- 67 res ยท 12 comm
- Plot / CTS / survey no.
- Survey No - 3/2 (Pt), 4/16 (Pt)
- Planning authority
- District Collector Office Thane
- Approved layout land
- 3,075 sq.m
- Land for this registration
- 3,075 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 6,191.82 sq.m
- Registered office
- Haware Infotech Park
- North
- DP Road
- South
- Adj Plot Survey No -2 -8 and 2 - 13
- East
- Adj Plot Survey No - 3 - 2 Part
- West
- Adj Plot Survey No - 4- 16 Part
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 62130IFSC ICIC0000151ICICI Bank Ltd., Shop No 14,15 16, Shri Ganesh Chs, Sector 1, Opp.Apna Bazar, Vashi, Navi Mumbai Dist.400703
Commencement Certificate documents
- CC Verification Mail - Haware Paramount Kalyan Phase IV.pdf
- CC FOR Phase IV and Amenity Plot_compressed (1).pdf
Buyer community
Connect with other buyers and owners of Haware Paramount Kalyan Phase IV โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Haware Paramount Kalyan Phase IV. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.