AAI NIWAS
S. NO. 50, H. NO. 1/7, CTS NO. 7738 TO 7743, Ambernath East, 421501
- Behind schedule. Possession is due Mar 2027 but construction is only at 40.9%.
Official RERA facts
- Registration
- P51700081063
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027
- Construction
- 40.9% complete
- Units sold
- 4 of 22
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
NILA PRAMOD AMRITE, MANDAR PRAMOD AMRITE, MEGHNA ASHUTOSH DEOSTHALI
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Dec 2025
- Floors
- 8
- Unit mix
- 18 res ยท 4 comm
- Plot / CTS / survey no.
- S. NO. 50, H. NO. 1/7, CTS NO. 7738 TO 7743
- Planning authority
- Ambernath Municipal council
- Approved layout land
- 182.65 sq.m
- Land for this registration
- 182.65 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 909.12 sq.m
- Registered office
- DATTA KUTIR,
- North
- ROAD
- South
- PROPERTY OF SAKET APARTMENT
- East
- PROPERTY OF HARIPRASAD BUILDING
- West
- BUNGLOW OF SHRI JUVEKAR
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- TJSB SAHAKARI BANK LTD โ 144478IFSC TJSB0000052GALA NO 15,16,17,18,19, GROUND FLOOR, PANVELKAR PLAZA, AMBERNATH (East) - 421 501
Commencement Certificate documents
- AMC CC.pdf
- AMC CC.pdf
Buyer community
Connect with other buyers and owners of AAI NIWAS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AAI NIWAS. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.