Under construction

Construction of 232 LIG TS on S.No. 263 p C.T.S No. 3525p Nr Bus depo Malwani Malad west Mumbai 95

by MUMBAI HOUSING AND AREA DEVELOPMENT BOARD

S no 263 part cts no3525part, Borivali, 400095

Caution
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 90.9%.

Official RERA facts

Registration
P51800000033
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jun 2017
Floors
9

Buyer community

Connect with other buyers and owners of Construction of 232 LIG TS on S.No. 263 p C.T.S No. 3525p Nr Bus depo Malwani Malad west Mumbai 95 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Construction of 232 LIG TS on S.No. 263 p C.T.S No. 3525p Nr Bus depo Malwani Malad west Mumbai 95. Real notes from real buyers beat any brochure.

Start a discussion