Under construction

AMRUT ELLEGANCE

by AMRUT ENTERPRISES

1743, 1743/1, 1743/2, 1744, F.P. No 172, Andheri, 400057

High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 39.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Vile Parle East / AirportUpper-mid

Institutional belt (colleges, airport) with steady society redevelopment.

Growth drivers:
Airport economy, Metro 3, education cluster.
Who buys here:
Airline/airport professionals, Parle loyalists.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800002223
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
39.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply3%
Sewerage (Chamber, Lines, Septic Tank , STP)3%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
13

Buyer community

Connect with other buyers and owners of AMRUT ELLEGANCE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AMRUT ELLEGANCE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.