Under construction

ADVENT PALAZZO

by ADVENT DEVELOPERS PRIVATE LIMITED

CTS NO. 6, Borivali, 400064

Jun 2018
Possession
86.4%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 86.4%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2018 per the RERA filing.
MaladMid-income

Retail-and-BPO hub with dense mid-income housing on both sides.

Growth drivers:
Mindspace offices, Link Road retail, Metro 2A.
Who buys here:
Mid-income families, first-time buyers.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800002649
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018
Construction
86.4% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply65%
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drains85%
Landscaping & Tree Planting10%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parking60%
Society Officenot started

Building & registration

RERA registered
Aug 2017
Floors
25

Buyer community

Connect with other buyers and owners of ADVENT PALAZZO โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ADVENT PALAZZO. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.