Under construction

10 Square

by VIJAY KAMDAR

100/1/2, Andheri, 400069

High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2018, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 82.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.
Andheri East / MarolMid-income

Office corridors (SEEPZ, MIDC) with value housing pockets between them.

Growth drivers:
Airport proximity, Metro 1/7, IT-park employment.
Who buys here:
Working couples prioritising commute over frills.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800004094
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally June 2018
Construction
82.7% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains60%
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting90%
Energy managemcntnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of 10 Square โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 10 Square. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.