Royal Fantasy Phase II

by Royal Fantasy Constructions Private Limited

CTS No 424, 424/1 to 33, Andheri, 400093

High risk
  • Possession delayed ~8 yrs. Originally promised Jun 2019, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Andheri East / MarolMid-income

Office corridors (SEEPZ, MIDC) with value housing pockets between them.

Growth drivers:
Airport proximity, Metro 1/7, IT-park employment.
Who buys here:
Working couples prioritising commute over frills.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800004649
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2019
Construction
83% complete
Units sold
67 of 68

RERA complaint record5 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Aug 2017
Floors
16
Unit mix
68 res ยท 0 comm
Architect
Arun Kumar Dube
Public authority
Slum Rehabilitation Authority

Buyer community

Connect with other buyers and owners of Royal Fantasy Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Royal Fantasy Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.