High risk
- Possession delayed ~5 yrs. Originally promised Jun 2018, now proposed Jul 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Jul 2023) has passed with construction at 51.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2023 per the RERA filing.
Official RERA facts
- Registration
- P51800005221
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2023originally June 2018
- Construction
- 51.8% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 20 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths40%
Water Supply15%
Sewerage (Chamber, Lines, Septic Tank , STP)15%
Storm Water Drains15%
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Water15%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements15%
Electrical meter room, sub-station, receiving station15%
Open Parking80%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 8
Buyer community
Connect with other buyers and owners of KALINA MARKET โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching KALINA MARKET. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.