CENTRONA NOVA-A

by ELEVATED AVENUE REALTY LLP

194 Part, Kurla, 400077

High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 39%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800005456
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally December 2026
Construction
39% complete
Units sold
224 of 226

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
35
Unit mix
226 res ยท 0 comm
Architect
Vishwas Satodia

Buyer community

Connect with other buyers and owners of CENTRONA NOVA-A โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching CENTRONA NOVA-A. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.