High risk
  • Possession delayed ~9 yrs. Originally promised Dec 2018, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51800006112
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2018
Construction
50.6% complete
Units sold
0 of 0