Under construction

Shankeshwar Apartment

by Navkar Developers

568,568/1 to 12, Borivali, 400097

High risk
  • Possession delayed ~6 yrs. Originally promised Sept 2020, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800006116
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally September 2020
Construction
85.8% complete
Units sold
21 of 95

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths85%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains35%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements55%
Electrical meter room, sub-station, receiving station84%

Building & registration

RERA registered
Aug 2017
Floors
23
Unit mix
94 res ยท 1 comm

Buyer community

Connect with other buyers and owners of Shankeshwar Apartment โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shankeshwar Apartment. Real notes from real buyers beat any brochure.

Start a discussion