High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed Jun 2022 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 90.9%.
MulundUpper-mid

Leafy eastern-suburb favourite with big redevelopment supply.

Growth drivers:
Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
Who buys here:
Eastern-suburb families upgrading within the area.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800006422
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally December 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record6 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
16

Buyer community

Connect with other buyers and owners of SUNFLOWER — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SUNFLOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.