All RERA projects
๐๏ธ
Jun 2024
Possession
89.5%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Jun 2021, now proposed Jun 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 89.5%.
Official RERA facts
- Registration
- P51800006560
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2024originally June 2021
- Construction
- 89.5% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC0060000003976873 Oct 2023SHANAYAA SHWETA CHAVAN vs Kartik ThakurLOP srno5.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Storm Water Drainsdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 16
Buyer community
Connect with other buyers and owners of SAI SOLITARE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAI SOLITARE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.